Environment· Prelims · GS-III
PM-DHARA: the Rs 1.86 lakh crore plan to move clean power
PM-DHARA pairs Rs 1,86,405 crore of intra-state transmission with 50 GWh of battery storage so that 135 GW of renewable power can actually reach the grid by FY 2032-33.
India can generate clean power faster than it can move it. Solar parks and wind farms in remote districts produce electricity that the wires cannot carry, so the power is curtailed, switched off even as it is generated. The PM-DHARA Scheme is the answer to that bottleneck: a Rs 1,86,405 crore plan, approved by the Union Cabinet on 30 September 2026, to strengthen intra-state transmission and deploy large-scale battery storage so renewable energy can actually reach the grid.
The problem: power that cannot travel
Renewable energy is generated where the sun and wind are, not where the demand is. Without adequate transmission, projects face curtailment: their output is wasted because the grid cannot take it. Solar power also stops at sunset, so evening demand must be met from elsewhere, and congestion on transmission lines adds to the strain. PM-DHARA, short for PM-Developing Harmonized and Accelerated Renewable-energy Access, is designed around exactly those three failures: evacuation, intermittency and congestion.
What PM-DHARA does
The scheme has a total project outlay of Rs 1,86,405 crore, with central financial support of Rs 54,082 crore, and a target completion of FY 2032-33. Its two objectives are to evacuate 135 GW of renewable energy by strengthening Intra-State Transmission Systems (InSTS) across states and union territories, and to deploy 50 GWh of Battery Energy Storage Systems (BESS) to handle intermittency, transmission congestion and peak-hour curtailment, and to meet demand during non-solar hours.
Component | Detail |
|---|---|
Intra-State Transmission Systems (InSTS) | Rs 1,36,378 crore under Green Energy Corridor-III |
Battery Energy Storage Systems (BESS) | Rs 50,000 crore for 50 GWh of storage |
Total project outlay | Rs 1,86,405 crore |
Central financial assistance | Rs 54,082 crore |
Target completion | FY 2032-33 |
The two halves: wires and batteries
The larger half is wires. Rs 1,36,378 crore goes to developing Intra-State Transmission Systems under Green Energy Corridor-III, the third phase of the Green Energy Corridor programme, so that renewable power generated in one part of a state can reach consumers across it. The smaller half is storage. Rs 50,000 crore deploys 50 GWh of battery storage, which absorbs surplus solar power during the day and releases it when the sun sets, smoothing the intermittency that makes grid operators cautious about renewable power. The central assistance of Rs 54,082 crore helps offset intra-state transmission charges, keeping power costs down for end users.
How it is built: bidding, cost-plus and the implementers
Greenfield projects are implemented through Tariff Based Competitive Bidding (TBCB), while brownfield network-strengthening works are executed on a Cost Plus Basis. State Transmission Utilities are the overall implementing agency, and Transmission Service Providers participate under TBCB on a Build-Own-Operate-Maintain (BOOM) model. The split matters for prelims: new lines are bid out competitively, upgrades to the existing network are done on cost-plus terms.
Why it matters for the 2030 and 2035 targets
PM-DHARA is the logistical backbone of the capacity targets. India has committed to 500 GW of installed non-fossil fuel capacity by 2030, and the scheme contributes to the target of 900 GW of installed non-fossil capacity by 2035. Capacity without evacuation is stranded generation: the panels and turbines exist, the power does not reach anyone. By pairing transmission with storage, the scheme attacks both halves of that failure at once, and it does so inside the states, where most of the evacuation bottleneck actually sits.
The execution test
The risks are the familiar ones for Indian infrastructure: land acquisition, right-of-way, coordination between state utilities and central agencies, and the pace at which battery storage costs fall and supply chains mature. The 2032-33 deadline gives the scheme seven years, and its success will be measured less in rupees sanctioned than in gigawatts that stop being curtailed. For mains answers, PM-DHARA is the strongest current example of the argument that the energy transition is now a transmission and storage problem, not a generation problem.
Key Terms
- PM-DHARA: PM-Developing Harmonized and Accelerated Renewable-energy Access, the scheme for intra-state transmission and battery storage for renewable energy.
- InSTS: Intra-State Transmission Systems, the within-state wires that carry power from generation sites to consumers.
- BESS: Battery Energy Storage Systems, which store surplus power and release it when generation falls.
- Green Energy Corridor-III: the third phase of the Green Energy Corridor programme, under which the transmission component of PM-DHARA is built.
- TBCB: Tariff Based Competitive Bidding, the route for greenfield transmission projects under PM-DHARA.
- Curtailment: the switching off of generated renewable power because the grid cannot take it.
- BOOM: Build-Own-Operate-Maintain, the model under which transmission service providers participate in PM-DHARA.
Practice questions
With reference to the PM-DHARA Scheme, consider the following statements:
1. It was approved by the Union Cabinet on 30 September 2026.
2. Its total project outlay is Rs 1,86,405 crore.
Show answer
Answer: (C) Both statements are correct: the Cabinet approved PM-DHARA on 30 September 2026 with an outlay of Rs 1,86,405 crore.
With reference to the PM-DHARA Scheme, consider the following statements:
1. The scheme aims to evacuate 135 GW of renewable energy.
2. The battery storage target under the scheme is 500 GWh.
Show answer
Answer: (A) Only statement 1 is correct: the battery storage target is 50 GWh, not 500 GWh.
With reference to the PM-DHARA Scheme, consider the following statements:
1. Central financial assistance of Rs 54,082 crore offsets intra-state transmission charges.
2. The scheme is to be completed by FY 2032-33.
Show answer
Answer: (C) Both statements are correct: the central assistance is Rs 54,082 crore and completion is targeted for FY 2032-33.
With reference to the implementation of the PM-DHARA Scheme, consider the following statements:
1. Greenfield projects are implemented through Tariff Based Competitive Bidding.
2. Transmission service providers participate on a build-own-operate-transfer model.
Show answer
Answer: (A) Only statement 1 is correct: providers participate on a build-own-operate-maintain (BOOM) model, not build-own-operate-transfer.
With reference to the PM-DHARA Scheme, consider the following statements:
1. The scheme supports the target of 900 GW of non-fossil capacity by 2035.
2. The scheme was approved by the Ministry of Power alone.
Show answer
Answer: (A) Only statement 1 is correct: the scheme was approved by the Union Cabinet, and it supports the 900 GW non-fossil target for 2035.
Answer key
- Q1: (c). Both statements are correct: the Cabinet approved PM-DHARA on 30 September 2026 with an outlay of Rs 1,86,405 crore.
- Q2: (a). Only statement 1 is correct: the battery storage target is 50 GWh, not 500 GWh.
- Q3: (c). Both statements are correct: the central assistance is Rs 54,082 crore and completion is targeted for FY 2032-33.
- Q4: (a). Only statement 1 is correct: providers participate on a build-own-operate-maintain (BOOM) model, not build-own-operate-transfer.
- Q5: (a). Only statement 1 is correct: the scheme was approved by the Union Cabinet, and it supports the 900 GW non-fossil target for 2035.
Mains Practice question
Q. Renewable capacity addition without evacuation is stranded generation. Analyse how PM-DHARA addresses the transmission and storage bottleneck, and the challenges in intra-state execution. (250 words)
Framing hintFrame the answer around the curtailment problem, then the two halves of the scheme, then the execution risks specific to intra-state works.
- Problem: renewables are generated far from demand; curtailment wastes output; solar stops at sunset.
- Transmission: Rs 1,36,378 crore for InSTS under Green Energy Corridor-III to evacuate 135 GW.
- Storage: Rs 50,000 crore for 50 GWh of batteries against intermittency and peak-hour curtailment.
- Support: Rs 54,082 crore central assistance offsets intra-state transmission charges.
- Execution: land and right-of-way, state utility capacity, TBCB versus cost-plus discipline, storage supply chains.
Q. The energy transition is now a transmission and storage problem, not a generation problem. Discuss with reference to PM-DHARA and the Green Energy Corridor programme. (150 words, 10 marks)
Framing hintUse the capacity-versus-evacuation contrast, then show how PM-DHARA pairs wires with batteries inside the states.
- Generation solved: 500 GW non-fossil by 2030 is a capacity target; the binding constraint has moved downstream.
- Wires: InSTS under Green Energy Corridor-III, 135 GW evacuation, TBCB for greenfield works.
- Storage: 50 GWh of batteries to shift solar power into non-solar hours.
- Measure of success: gigawatts no longer curtailed, not rupees sanctioned.
Frequently asked questions
What does PM-DHARA stand for?
PM-Developing Harmonized and Accelerated Renewable-energy Access. It is the scheme to strengthen intra-state transmission and deploy battery storage for renewable energy evacuation.
What is the outlay of PM-DHARA?
Rs 1,86,405 crore in total, with central financial assistance of Rs 54,082 crore. Of the total, Rs 1,36,378 crore is for intra-state transmission under Green Energy Corridor-III and Rs 50,000 crore is for 50 GWh of battery storage.
Why does renewable energy need battery storage?
Solar power stops at sunset while demand continues into the evening. Batteries absorb surplus power during the day and release it later, reducing curtailment and easing congestion on transmission lines.
Who implements PM-DHARA?
State Transmission Utilities are the overall implementing agency. Greenfield projects go through Tariff Based Competitive Bidding, with Transmission Service Providers participating on a build-own-operate-maintain model, while brownfield upgrades run on a cost-plus basis.
How does PM-DHARA connect to India's capacity targets?
It is the evacuation backbone for 500 GW of non-fossil capacity by 2030 and supports the 900 GW non-fossil target for 2035. Without it, new renewable capacity would be stranded by the wires.